INNERSIDE FINISHING WORK OF TRAINING HALL BUILDING |
|
Name of Project :- Innerside finishing work of Training Hall building (Young Star Club) F/Y:- 060/61 Address :- Dorpu bazar, salleri VDC - 7, Solukhumbu. |
| S.N. | Description of Works | No. | Length(m) | Bradth(m) | Height(m) | Quantity | Unit | Unit rate | Amount | Remarks. |
| 1 | Local wood work for side ceiling,flooring etc of good finishing with bothside lapping joints as per direction all complete. | |||||||||
| Flooring | 1 | 22.80 | 6.30 | 143.64 | ||||||
| Do | 1 | 6.60 | 3.30 | 21.78 | ||||||
| False ceiling | 1 | 22.80 | 6.30 | 143.64 | ||||||
| Do | 1 | 6.60 | 3.30 | 21.78 | ||||||
| Side ceiling in wall | 1 | 65.10 | 3.60 | 234.36 | ||||||
| Total Area | 565.20 | |||||||||
| Deduction: | ||||||||||
| Door | 4 | 1.20 | 2.10 | 10.08 | ||||||
| Window | 9 | 1.00 | 1.10 | 9.90 | ||||||
| Total Area | 19.98 | |||||||||
| Net Area ( 565.20 - 19.98) Sqm. | 545.22 | sqm | 245.34 | 133764.27 | ||||||
| Total amount (NRs.) | 133764.27 | |||||||||
| In words :- Rs. one lac thirty three thousand seven hundred sixty four and paisa twenty seven only. | ||||||||||
|