Name  of Project :- Football ground Construction Work (Young Star Club)                                                   F/Y:- 060/61

Address :- Dorpu bazar, salleri VDC - 7, Solukhumbu. 

                   
S.N. Description of Works No. Length(m) Bradth(m) Height(m) Quantity Unit Unit rate Amount Remarks.
1 Site clearance work before and after completion of the construction work as per directiion and instruction all complete.   L.S.     1.00 Job L.S. 2000.00  
2 Earthwork in excavation in boulder mixed soil for foundation work including 1.50m lift and 10m disposal lead facility all comlete.                  
    Garden separation wall 1 18.00 0.60 0.30 3.24        
  Do 1 27.00 0.60 0.30 4.86        
    Parapet  1 31.00 1.80 0.30 16.74        
  Do 1 35.00 3.00 0.30 31.50        
    Raised plateform (semi circular of 6m. dia.) 1 3.14 36.00 0.60 67.82        
    Retaining structure (wall) 1 35.00 0.60 0.30 6.30        
  Do 1 30.00 1.35 0.30 12.15        
  Do 1 40.00 1.90 0.30 22.80        
  Do 1 23.00 1.50 0.30 10.35        
Total quantity 175.76 Cum 245.66 43178.18  
3 Dry stone masonry wall work of stone laying with proper joints, bonding & in desined slope or straight in vertical as per direction and instruction all complete.                  
    Garden separation wall 1 18.00 0.60 1.20 12.96        
  Do 1 27.00 0.60 1.20 19.44        
    Parapet wall - 1st step 1 31.00 1.80 1.50 83.70        
    Parapet wall - 2nd step 1 31.00 1.20 0.20 7.44        
    Parapet wall - 3rd step 1 31.00 0.60 0.20 3.72        
    Parapet wall - 1st step 1 35.00 3.00 1.50 157.50        
    Parapet wall - 2nd step 1 35.00 2.40 0.20 16.80        
    Parapet wall - 3rd step 1 35.00 1.80 0.20 12.60        
    Parapet wall - 4th step 1 35.00 1.20 0.20 8.40        
    Parapet wall - 5th step 1 35.00 0.60 0.20 4.20        
    Raised plateform (semi circular of 6m. dia.) 1 3.14 36.00 3.60 406.94        
    Retaining structure (wall) 1 35.00 0.60 1.50 31.50        
  Do 1 30.00 0.98 3.00 88.20        
  Do 1 40.00 1.25 4.30 215.00        
  Do 1 23.00 1.05 3.00 72.45        
Total Quantity 1140.85 cum 1434.48 1636532.25  
4 Flagstone of 3'x0'5"x0'1.5"in size paving in courtyard & arround the garden with straight in position, joints etc as per direction all complete. 1 27.00 2.00   54.00        
  Do 1 24.50 4.00   98.00        
  Do 1 18.00 2.40   43.20        
    Top of plate form 1 3.14 36.00   113.04        
    Parapet wall 3 31.00 0.60   55.80        
    Parapet wall 5 35.00 0.60   105.00        
Total Area 469.04 sqm 763.00 357877.52  
Grand Total Amount (NRs.) 2039587.95  
In words :- Rs. Twenty lac thrity nine thousand five hundred eighty seven and paisa ninety five only.
 
 