FOOTBALL GROUND CONSTRUCTION WORK |
|
|
|
Name of Project :- Football ground Construction Work (Young Star Club) F/Y:- 060/61 Address :- Dorpu bazar, salleri VDC - 7, Solukhumbu. |
||||||||||
| S.N. | Description of Works | No. | Length(m) | Bradth(m) | Height(m) | Quantity | Unit | Unit rate | Amount | Remarks. |
| 1 | Site clearance work before and after completion of the construction work as per directiion and instruction all complete. | L.S. | 1.00 | Job | L.S. | 2000.00 | ||||
| 2 | Earthwork in excavation in boulder mixed soil for foundation work including 1.50m lift and 10m disposal lead facility all comlete. | |||||||||
| Garden separation wall | 1 | 18.00 | 0.60 | 0.30 | 3.24 | |||||
| Do | 1 | 27.00 | 0.60 | 0.30 | 4.86 | |||||
| Parapet | 1 | 31.00 | 1.80 | 0.30 | 16.74 | |||||
| Do | 1 | 35.00 | 3.00 | 0.30 | 31.50 | |||||
| Raised plateform (semi circular of 6m. dia.) | 1 | 3.14 | 36.00 | 0.60 | 67.82 | |||||
| Retaining structure (wall) | 1 | 35.00 | 0.60 | 0.30 | 6.30 | |||||
| Do | 1 | 30.00 | 1.35 | 0.30 | 12.15 | |||||
| Do | 1 | 40.00 | 1.90 | 0.30 | 22.80 | |||||
| Do | 1 | 23.00 | 1.50 | 0.30 | 10.35 | |||||
| Total quantity | 175.76 | Cum | 245.66 | 43178.18 | ||||||
| 3 | Dry stone masonry wall work of stone laying with proper joints, bonding & in desined slope or straight in vertical as per direction and instruction all complete. | |||||||||
| Garden separation wall | 1 | 18.00 | 0.60 | 1.20 | 12.96 | |||||
| Do | 1 | 27.00 | 0.60 | 1.20 | 19.44 | |||||
| Parapet wall - 1st step | 1 | 31.00 | 1.80 | 1.50 | 83.70 | |||||
| Parapet wall - 2nd step | 1 | 31.00 | 1.20 | 0.20 | 7.44 | |||||
| Parapet wall - 3rd step | 1 | 31.00 | 0.60 | 0.20 | 3.72 | |||||
| Parapet wall - 1st step | 1 | 35.00 | 3.00 | 1.50 | 157.50 | |||||
| Parapet wall - 2nd step | 1 | 35.00 | 2.40 | 0.20 | 16.80 | |||||
| Parapet wall - 3rd step | 1 | 35.00 | 1.80 | 0.20 | 12.60 | |||||
| Parapet wall - 4th step | 1 | 35.00 | 1.20 | 0.20 | 8.40 | |||||
| Parapet wall - 5th step | 1 | 35.00 | 0.60 | 0.20 | 4.20 | |||||
| Raised plateform (semi circular of 6m. dia.) | 1 | 3.14 | 36.00 | 3.60 | 406.94 | |||||
| Retaining structure (wall) | 1 | 35.00 | 0.60 | 1.50 | 31.50 | |||||
| Do | 1 | 30.00 | 0.98 | 3.00 | 88.20 | |||||
| Do | 1 | 40.00 | 1.25 | 4.30 | 215.00 | |||||
| Do | 1 | 23.00 | 1.05 | 3.00 | 72.45 | |||||
| Total Quantity | 1140.85 | cum | 1434.48 | 1636532.25 | ||||||
| 4 | Flagstone of 3'x0'5"x0'1.5"in size paving in courtyard & arround the garden with straight in position, joints etc as per direction all complete. | 1 | 27.00 | 2.00 | 54.00 | |||||
| Do | 1 | 24.50 | 4.00 | 98.00 | ||||||
| Do | 1 | 18.00 | 2.40 | 43.20 | ||||||
| Top of plate form | 1 | 3.14 | 36.00 | 113.04 | ||||||
| Parapet wall | 3 | 31.00 | 0.60 | 55.80 | ||||||
| Parapet wall | 5 | 35.00 | 0.60 | 105.00 | ||||||
| Total Area | 469.04 | sqm | 763.00 | 357877.52 | ||||||
| Grand Total Amount (NRs.) | 2039587.95 | |||||||||
| In words :- Rs. Twenty lac thrity nine thousand five hundred eighty seven and paisa ninety five only. | ||||||||||
|